01. For which revenue-carrying cost objects does the system perform results analysis?
There are 3 correct answers to this question.
a) Cost center
b) Business processes
c) Internal order
d) Work breakdown structure
e) Customer service orders
02. What does the calculation of a condition type in the costing sheet of CO-PA depend on?
There are 2 correct answers to this question.
a) Valuation
b) Calculation type
c) Segment
d) Condition class
03. Which controls can you set when you determine a characteristic derivation?
There are 3 correct answers to this question.
a) Valuation calculation
b) System response when unsuccessful
c) Display authority
d) Overwriting authority
e) Conditions for execution
04. Which process can you use to credit internal orders during period-end closing?
Please choose the correct answer.
a) Assessment
b) Distribution
c) Indirect activity allocation
d) Periodic reposting
05. You post an expense line in an accounting document and enter an internal order and a cost center as the account assignments. After posting, the system allows you to settle the posted values from the internal order.
Which settings do the cost center and internal order have?
Please choose the correct answer.
a) Real internal order
Real cost center
b) Statistical internal order
Statistical cost center
c) Statistical internal order
Real cost center
d) Real internal order
Statistical cost center
06. A profit center standard hierarchy contains all profit centers that are assigned to which organizational unit?
Please choose the correct answer.
a) Client
b) Plant
c) Controlling area
d) Operating concern
07. In which SAP S/4HANA components can you report the results of the results analysis?
There are 3 correct answers to this question.
a) Profitability analysis
b) Inventory management
c) Profit center accounting
d) Sales and distribution
e) Financial accounting
08. What must the referenced cost estimate and the receiving cost estimate have in common?
Please choose the correct answer.
a) The cost component structure
b) The company codes
c) The quantity structure
d) The plant
09. Which object controls the tiles a business user can assign to their SAP Fiori launchpad?
Please choose the correct answer.
a) Tile group
b) App library
c) App finder
d) Tile catalog
10. You need to assign a company code to a controlling area. Which settings must be identical for both organizational objects?
There are 2 correct answers to this question.
a) Operational Chart of accounts
b) Currency
c) Operational Posting period
d) Fiscal year variant