SAP Activate Project Manager Sample Questions:

QUESTIONS

01. What can you do in the SAP Roadmap Viewer tool?
Please choose the correct answer.
a) Create a customer-specific version of a roadmap.
b) Navigate detailed Solution Implementation Roadmaps.
c) Download full roadmap content for offline navigation.
d) Comment on Deliverables and Tasks within Roadmaps.

02. How do you gain access to the SAP Activate Methodology Jam site?
Please choose the correct answer.
a) Register on SAP Service Marketplace
b) Send e-mail to SAP contact address
c) Submit e-mail address via on-line form
d) Join SAP S/4HANA group on SAP Community Network

03. Where can you find Project Library Accelerators?
Please choose the correct answer.
a) SAP Best Practices Explorer
b) SAP Cloud Appliance Library
c) Fully Activated Appliance
d) SAP Roadmap Viewer

04. What does SAP Activate recommend to keep team members informed and aligned?
Please choose the correct answer.
a) Daily status meeting with project manager
b) Daily team stand-up meeting
c) Daily e-mail status updates to project manager
d) Daily progress review meeting with sponsor

05. What are the three elements of SAP Activate?
There are 3 correct answers to this question.
a) Content
b) Methodology
c) Focused Build
d) Tools
e) SAP Solution Manager

06. What is the minimum number of Quality Gates mandated for SAP S/4HANA transition projects?
Please choose the correct answer.
a) 2
b) 3
c) 4
d) 5

07. Which activities are critical for delivering Agile projects?
There are 2 correct answers to this question.
a) Retrospective agenda creation
b) Sprint planning
c) Release planning
d) Blueprint scheduling

08. In which phase of the SAP Activate methodology does the team complete the Cut-over Rehearsal?
Please choose the correct answer.
a) Prepare
b) Explore
c) Realize
d) Deploy

09. Who determines the priority of user stories in the backlog of an Agile project?
Please choose the correct answer.
a) Project Manager
b) Project Team
c) SCRUM Master
d) Product Owner

10. What is the correct order of the SAP Activate Methodology phases?
Please choose the correct answer.
a) Plan -> Design -> Build -> Operate
b) Discover -> Prepare -> Explore -> Realize -> Deploy -> Run
c) Plan -> Build -> Run -> Sustain
d) Prepare -> Discover -> Explore -> Realize -> Deploy -> Run

If you have any feedback, pl send us on [email protected]

  • Sign In / Sign Up to access FREE Sample Test (No Credit Card or Financial Info Required)
  • Disclaimer: All trademarks, trade names, product names and logos appearing on the site are the property of their respective owners. The site www.erpprap.com is in no way affiliated with SAP SE.