SAP Activate Project Manager Sample Questions:
QUESTIONS
DONE
C_S4FCF_2020 / C_S4FCF_2021
01. What happens when you stop a replication in SAP Landscape Transformation (SLT)?
There are 2 correct answers to this question.
a) SLT configuration is deactivated.
b) Database triggers in the source are deleted.
c) Logging table in the source is deleted.
d) SLT load and replication object are reset.
02. On which level can you activate central payment?
Please choose the correct answer.
a) Business partner
b) Company code
c) Client
d) Payment run ID
03. Which event triggers the transfer of COGS to the Central Finance system?
Please choose the correct answer.
a) Production order settlement
b) Sales order creation
c) Invoice receipt
d) Goods delivery
04. What are the capabilities of the Customer/Vendor Integration (CVI) business function?
There are 2 correct answers to this question.
a) Allows bi-directional replication of business partner, customer master, and vendor master
b) Integrates the business partner, customer master, and vendor master
c) Checks for duplicates of business partner, customer master, and vendor master
d) Replaces the customer master and vendor master with business partners
05. Which of the following steps are key factors for a successful Central Finance implementation?
There are 2 correct answers to this question.
a) Migrate from a two-tier architecture to a three-tier architecture.
b) Involve business process owners during system design.
c) Define strong master data governance processes.
d) Reorganize source systems.
06. What is a prerequisite to start the replication of internal CO documents?
Please choose the correct answer.
a) Cost elements in the CO document must be primary cost elements.
b) CO document must be linked to an FI document.
c) Sender system must be an SAP S/4 system.
d) CFIN_SOURCE_SET table must be configured.
07. Which detail settings can you define for classic Profit Center Accounting (EC-PCA) postings in Central Finance?
There are 3 correct answers to this question.
a) Fiscal year variant
b) Dedicated ledger group
c) Offsetting account for one-sided EC-PCA posting
d) Posting key
e) Separate document type
08. Which settings for the FI/CO initial load do you define in the CFIN_SOURCE_SET table in the source system?
There are 3 correct answers to this question.
a) Periods for documents
b) Substitution accounts
c) Controlling area
d) Fiscal year for balances
e) Company code
09. Which of the following is a characteristic of a BAPI?
Please choose the correct answer.
a) BAPIs are closely linked to business events.
b) BAPIs can be used exclusively within the SAP system.
c) BAPIs have a presentation layer.
d) BAPIs CANNOT be changed after they are released.
10. What must you do to replicate project definitions and WBS elements?
There are 2 correct answers to this question.
a) Reset the SAP Landscape Transformation staging tables.
b) Configure the inbound and outbound ALE.
c) Activate the Central Finance accounting interface.
d) Set up the Application Interface Framework.
If you have any feedback, pl send us on [email protected]