SAP Activate Project Manager Sample Questions:
QUESTIONS
01. Which of the following organizational assignments can be stored in the internal order master?
There are 3 correct answers to this question.
a) Segment
b) Profit Center
c) Storage Location
d) Business Area
e) Plant
02. You want to save your previous standard cost center hierarchy from 2015 for reporting purposes and create a new one for 2016. Which name is used for the copied hierarchy?
Please choose the correct answer.
a) Original name plus system-defined suffix
b) Original name plus user-defined suffix
c) User-defined prefix plus original name
d) System-defined prefix plus original name
03. What selection criteria can be used to copy actuals to a target planning version?
There are 3 correct answers to this question.
a) Cost centers
b) Cost elements
c) Fiscal year
d) Actual version
e) Period
04. You can plan business allocations on your internal order and update the sender cost center automatically. However, when you try to do this in the system, the planned values are not updated on your cost center.
What should you check to solve this problem?
Please choose the correct answer.
a) The integrated planning indicator in the planning version
The order master
b) The integrated planning with cost centers/business processes indicator in the planning version
The order category
c) The integrated planning indicator in the planning version
The order type
d) The integrated planning with cost centers/business processes indicator in the planning version
The order master
05. What are typical use cases for product cost by period?
There are 2 correct answers to this question.
a) Very flexible production environment
b) Customer-specific production
c) Continuous production
d) High volume production
06. You would like to use product cost controlling by sales orders in a make-to-order (MTO) production with sales order stock. How should you configure the system?
Please choose the correct answer.
a) Account assignment category: E
Special stock: E
b) Account assignment category: M
Special stock: E
c) Consumption posting indicator: Blank
Special stock: E
d) Consumption posting indicator: E
Special stock: Blank
07. You post a document to Financial Accounting with assignment to a cost center. The General Ledger view of the posted document does NOT contain the profit center.
What do you need to check to resolve the issue?
There are 2 correct answers to this question.
a) Assignment of “profit center update” scenario to leading ledger
b) Availability of profit center field in table FAGLFLEXT
c) Activation of classic Profit Center Accounting (EC-PCA)
d) Profit center assignment in cost center master data
08. What do you valuate in the inventory cost estimate?
Please choose the correct answer.
a) Current quantity structure with the tax-based prices and the commercial prices
b) Current quantity structure with the planned prices
c) Planned quantity structure with the planned prices
d) Current quantity structure with the current prices
09. Each billing document creates line items in CO-PA. For which characteristics do you need to create specific derivation rules?
There are 2 correct answers to this question.
a) Product group
b) Business area
c) Sales district
d) Ship-to-party
10. Which of the following organizational unit assignments is correct?
Please choose the correct answer.
a) Plant → Company code → Operating concern → Controlling Area
b) Company code → Plant → Controlling Area → Operating concern
c) Plant → Company code → Controlling Area → Operating concern
d) Company code → Plant → Operating concern → Controlling Area
If you have any feedback, pl send us on [email protected]